Carbon Capture and Storage

As part of the HyNet North West Low Carbon Project, Eni will develop and operate offshore and onshore transportation and storage of CO2 captured from industrial sites in Northwest England at the Liverpool Bay offshore oil and gas facilities in line with its mission to transition towards a low-carbon future.Â

The Protos pipeline is one of several pipelines being installed as part of the Carbon Capture network.

Client
Eni
Industry
Carbon Capture and Storage
Location
United Kingdom
Services
HAZID
ENVID
HAZOP
SIL Classification (via Risk Graph)
SIMOPS
Project Risk Assessment
Year
2024
Client
  • Eni
Industry
  • Carbon Capture and Storage
Location
  • United Kingdom
Services
  • ENVID
  • HAZID
  • HAZOP
  • Project Risk Assessment
  • SIL Classification (via Risk Graph)
  • SIMOPS
Year
  • 2024

The challenge

To address potential risks and hazards associated with the project during the Front End Engineering Design (FEED) phase, Process Risk Consulting were commissioned to facilitate the Project Risk Assessment, Hazard Identification (HAZID), Environmental Identification (ENVID), Simultaneous Operations (SIMOPS), Hazard and Operability (HAZOP) and Safety Integrity Level (SIL) Allocation Workshops , in line with ENI Guidelines for the Protos pipeline and associated facilities.

The scope of workshop included all of the onshore transport and storage facilities including several onshore pipelines and Above Ground Installations (AGI’s).

As part of the HyNet North West Low Carbon Project, Eni will develop and operate offshore and onshore transportation and storage of CO2 captured from industrial sites in Northwest England at the Liverpool Bay offshore oil and gas facilities in line with its mission to transition towards a low-carbon future.Â

The Runcorn pipeline is one of several pipelines being installed as part of the Carbon Capture network.

Client
Eni
Industry
Carbon Capture and Storage
Location
United Kingdom
Services
HAZID
ENVID
HAZOP
SIL Classification (via Risk Graph)
SIMOPS
Project Risk Assessment
Year
2024
Client
  • Eni
Industry
  • Carbon Capture and Storage
Location
  • United Kingdom
Services
  • ENVID
  • HAZID
  • HAZOP
  • Project Risk Assessment
  • SIL Classification (via Risk Graph)
  • SIMOPS
Year
  • 2024

The challenge

To address potential risks and hazards associated with the project during the Front End Engineering Design (FEED) phase, Process Risk Consulting were commissioned to facilitate the Project Risk Assessment, Hazard Identification (HAZID), Environmental Identification (ENVID), Simultaneous Operations (SIMOPS), Hazard and Operability (HAZOP) and Safety Integrity Level (SIL) Allocation Workshops , in line with ENI Guidelines for the Runcorn pipeline and associated facilities.

The scope of workshop included all of the onshore transport and storage facilities including several onshore pipelines and Above Ground Installations (AGI’s).

Associated British Ports (ABP) is seeking to construct, operate and maintain the Immingham Green Energy Terminal (IGET) – a new multi-user liquid bulk green energy terminal located on the eastern side of the Port of Immingham – the first of its kind in the world.

Air Products would be the first customer to use the new facility for the production of green hydrogen alongside a second operator for the filling of Carbon Dioxide onto vessels to be injected into offshore wells.

Client
Associated British Ports
Industry
Carbon Capture and Storage

Ammonia Cracking to Hydrogen

Marine
Location
United Kingdom
Services
EERA

HSE Designers Legislation Review

HSE Management Plan

HSE Design Philosophy
Year
2024
Client
  • Associated British Ports
Industry
  • Ammonia Cracking to Hydrogen
  • Carbon Capture and Storage
  • Marine
Location
  • United Kingdom
Services
  • EERA
  • HSE Design Philosophy
  • HSE Designers Legislation Review
  • HSE Management Plan
Year
  • 2024

The challenge

Following on from their input during RIBA 2, Process Risk Consulting were commissioned to provide independent Technical Safety Design input into the design of the berth ensuring that the design is in accordance with relevant local and end-user requirements for the RIBA 3 phase of the project.

Process Risk Consulting developed the following deliverables during the RIBA 3 phase of the project:

  • HSE Designer’s Legislation Review
  • HSE Designer’s Management Plan
  • HSE Design Philosophy
  • Escape, Evacuation and Rescue Analysis

In addition to the above, Process Risk Consulting also contributed towards other design developments, workshops (i.e. Human Factors Engineering) and preparing the specification for additional works to be conducted during the Engineering, Procurement and Construction (EPC) phase of the project.

As part of the HyNet North West Low Carbon Project, Eni will develop and operate offshore and onshore transportation and storage of CO2 captured from industrial sites in Northwest England at the Liverpool Bay offshore oil and gas facilities in line with its mission to transition towards a low-carbon future.

Client
Eni
Industry
Carbon Capture and Storage
Location
United Kingdom
Services
HAZID
ENVID
HAZOP
SIL Classification (via Risk Graph)
SIMOPS
Project Risk Assessment
Year
2024
Client
  • Eni
Industry
  • Carbon Capture and Storage
Location
  • United Kingdom
Services
  • ENVID
  • HAZID
  • HAZOP
  • Project Risk Assessment
  • SIL Classification (via Risk Graph)
  • SIMOPS
Year
  • 2024

The challenge

To address potential risks and hazards associated with the project during the Front End Engineering Design (FEED) phase, Process Risk Consulting were commissioned to facilitate the Project Risk Assessment, Hazard Identification (HAZID), Environmental Identification (ENVID), Simultaneous Operations (SIMOPS), Hazard and Operability (HAZOP) and Safety Integrity Level (SIL) Allocation Workshops , in line with ENI Guidelines for the Padeswood pipeline and associated facilities.

The scope of workshop included all of the onshore transport and storage facilities including several onshore pipelines and Above Ground Installations (AGI’s).

The project will see CO2 from enfinium’s flagship Ferrybridge, West Yorkshire incinerator captured and transported to Navigator’s Teesside storage facility which will then be transported offshore for permanent storage.

Client
  • Navigator Terminals
Industry
  • Carbon Capture and Storage
Location
  • United Kingdom
Services
  • ENVID
  • HAZID
Year
  • 2023

The challenge

To address potential risks for the first of a kind transport of Carbon Dioxide, Process Risk Consulting were commissioned to chair a Hazard Identification (HAZID) and Environmental Identification (ENVID) workshop for the project to cover the entire scope from emitter take-off to connection with the downstream operators injection pipeline in order to identify potential hazards, ensuring that they are suitably protected and mitigated.

As part of the HyNet North West Low Carbon Project, Eni will develop and operate offshore and onshore transportation and storage of CO2 captured from industrial sites in Northwest England at the Liverpool Bay offshore oil and gas facilities in line with its mission to transition towards a low-carbon future.

Client
Eni
Industry
Carbon Capture and Storage
Location
United Kingdom
Services
HAZID
ENVID
HAZOP
SIL Classification (via Risk Graph)
SIMOPS
Project Risk Assessment
Year
2024
Client
  • Eni
Industry
  • Carbon Capture and Storage
Location
  • United Kingdom
Services
  • ENVID
  • HAZID
Year
  • 2023

The challenge

To address potential safety and environmental risks and hazards associated with the project, Process Risk Consulting were commissioned to facilitate a series of Hazard Identification (HAZID) and Environmental Identification (ENVID) Workshop, in line with ENI Qualitative Risk Assessment guidelines – OPI-HSE-024-ENI-SPA-R01.

The scope of workshop included all of the onshore facilities, onshore pipelines, subsea pipelines, onshore conditioning and storage facilities, offshore platform and well injection.

Associated British Ports (ABP) is seeking to construct, operate and maintain the Immingham Green Energy Terminal (IGET) – a new multi-user liquid bulk green energy terminal located on the eastern side of the Port of Immingham – the first of its kind in the world.

Air Products would be the first customer to use the new facility for the production of green hydrogen alongside a second operator for the filling of Carbon Dioxide onto vessels to be injected into offshore wells.

Client
Associated British Ports
Industry
Carbon Capture and Storage

Ammonia Cracking to Hydrogen

Marine
Location
United Kingdom
Services
EERA

HSE Designers Legislation Review

HSE Management Plan

HSE Design Philosophy
Year
2024
Client
  • Associated British Ports
Industry
  • Ammonia Cracking to Hydrogen
  • Carbon Capture and Storage
  • Marine
Location
  • United Kingdom
Services
  • HAZID
  • Marine Exclusion Zone
  • Quantitative Risk Assessment
  • Technical Safety Design
Year
  • 2023

The challenge

 Process Risk Consulting were commissioned to provide independent Technical Safety Design input into the design of the berth ensuring that the design is in accordance with relevant local and end-user requirements for the RIBA 2 phase of the project.

Process Risk Consulting developed the following deliverables during the RIBA 2 phase of the project:

    • Combined Coarse Quantitative Risk Assessment (QRA)

    • HAZID Study

    • Identification of the Marine Exclusion Zone for Ammonia and CO2 vessels